Caledyne全金属井下封隔系统(英)

[加入收藏][字号: ] [时间:2009-06-03  来源:E&P  关注度:0]
摘要:简介:Caledyne公司的全金属井下封隔系统,实现了真正的全部金属体封隔油井,安全可靠,能够抵抗极端条件。该公司采用了全金属封隔的可回收桥塞(RBP),最近应用于马来西亚Bunga Kekwa一项目中,来临时封堵一井。该RBP下于7,24...
简介:Caledyne公司的全金属井下封隔系统,实现了真正的全部金属体封隔油井,安全可靠,能够抵抗极端条件。该公司采用了全金属封隔的可回收桥塞(RBP),最近应用于马来西亚Bunga Kekwa一项目中,来临时封堵一井。该RBP下于7,244 英尺处,经过两个月的井下作业,取出后完好无损,显示了其良好的机械性能。


Caledyne’s metal-to-metal (MTM) downhole seal system provides a complete metal barrier that is reliable, durable, and resistant to extreme conditions.

The company’s retrievable bridge plug (RBP), which incorporates the MTM seal, was recently deployed for Talisman on the Bunga Kekwa project in Malaysia to temporarily plug a well.

The RBP was installed to a depth of 7,244 ft (2,208 m). The assembly was run, and the setting tool activated, which sheared off the bridge plug and removed it from the well.

Well deviation at the RBP was 45° and was successfully pressure-tested to 350 psi. After one hour, a straight-line pressure test with zero dropoff was recorded, and after 24 hours, there was no pressure buildup in the tubing. A debris catcher was then installed above the RBP to keep out cuttings.

A second tubing cut was required below the original cut after problems were encountered during repair activities. Because this process was performed without a debris catcher, considerable debris landed on top of the RBP. Multiple bailer and venture runs were carried out to remove the debris. The new completion components were installed a month after the RBP.

When the plug was removed, the large amount of debris prevented the pulling tool from latching the fishing neck on the RBP, which resulted in further bailing runs to remove debris.

At this point, the plug was released but could not be pulled. Several maximum overpulls of 30,000 lbf were applied that eventually moved the plug slowly uphole.

With the plug removed, the RBP appeared to be in good condition with the MTM seal fully intact, sitting just above gauge diameter. The resilience of the RBP reflects the mechanical strength, construction, integrity, and design of the MTM seal, which had been downhole for two months.

Since this initial deployment, the operator has ordered several additional RBP units for similar reservoir applications. 

杨宝剑 是振威(全球)石油网的高级技术编辑,在石油技术资讯行业有八年的学识和经验。他源源不断地提供石油行业全球最新的技术创新、研发成果、现场应用情况等信息。如果你对该项新技术有任何的疑问,或者对“新技术新产品”未来的内容有任何问题或建议,请联系杨宝剑编辑 +86 10-58236512 Email:allenyo@zhenweiexpo.com 欢迎与行业互动!

          您的分享是我们前进最大的动力,谢谢!